Union Grievance 04-01, dated July 21, 2004, on behalf of the Grievor, Robert MacDonald, alleging that the Employer discharged the Grievor in violation of Article 2.1 of the Collective Agreement between the parties effective January 1, 1999 — January 1, 2002, which the parties agree is the Collective Agreement applicable here. At the outset of the hearing in this matter the parties agreed that I am properly seized of it, that I should remain seized after the issue of this award to deal with any matters arising from its application and that all time limits, either pre-or post-hearing, are waived. The Union sought an order rescinding the letter of discipline dis­charging the Grievor and granting him full redress.